Maes Twnti, Morfa Nefyn
Home > Ongoing Projects > Maes Twnti, Morfa Nefyn
A development of 9 two and three bedroom houses in timber frame construction.
Foundations are traditional strip footings incorporating a beam and insulation infill ground floor slab system to achieve greater U-Values
Designed to EPC A, Air Source Heat pumps (ASHP), Mechanical Ventilation heat Recovery (MVHR) and Photovoltaic Panels (PV) Panels fitted to each house.
The client is a registered Social Landlord.
Commenced in April 2026, Slated for completion May 2027
- Aerial view of housing development under construction.
- Overhead view of active construction site.
- Drone view of timber-framed homes under construction.
- Mobile crane on construction site.
- Scaffolded housing block under construction.
- Timber roof trusses being installed.
- Timber roof frame under construction.
- Roof rafters being installed.
- Internal timber wall framing.
- Timber frame interior under construction.
- The building side castlemead will be working on in Maes Twnti, Morfa Nefyn
- Close view of the JCB digging the ground at Maes Twnti, Morfa Nefyn
- Rear view of a person inside the JCB working on moving gravel in Maes Twnti, Morfa Nefyn
- A person inside the digger digging the ground in Maes Twnti, Morfa Nefyn
- View of the ground after been digged up and cemented
- Close view of the level of ground they've digged up in Maes Twnti, Morfa Nefyn
- Long view of a person inside a JCB moving gravel in Maes Twnti, Morfa Nefyn
- Aerial view of the building side Castlemead are working on in Maes Twnti, Morfa Nefyn
- Aerial view of the work Castlemead have done in Maes Twnti, Morfa Nefyn
- Aeriel view of the work that's been done already by Castlemead in Maes Twnti, Morfa Nefyn